How long does a joiner's website take to build? A phase-by-phase build log

A joiner I spoke to earlier this year had been waiting eleven weeks. He had paid half up front in May, sent over a folder of photographs, and since then had received one holding page with his logo on it and increasingly vague replies. He wanted to know whether eleven weeks was normal for a website, or whether he had been had.

It is a fair question and nobody in the trade answers it honestly, because the honest answer is unflattering to a lot of people who build websites. Eleven weeks is not normal. It is also not unusual, which is a different thing.

So this is the calendar rather than the sales pitch: what each phase of a seven page joinery site actually takes, which of those phases is genuinely slow, and which one is the reason most British trade websites drift. There is one clear answer to that last part, and it is not the building.

Quick answer

About eight working days from photographs to live, for a seven page joinery site built by somebody who does this full time. Doing it yourself on Wix or Squarespace takes three to eight weeks of evenings. A UK freelancer usually quotes four to twelve. The build is rarely the slow part in any of them: waiting on photographs is.

Where the eight days actually go

On a seven page joinery site the largest single block of elapsed time is not design or code, it is the gap between agreeing to start and receiving usable photographs of finished work.

Eight working days, split by phase

Sitework's own phase breakdown for a seven page carpentry and joinery site. Elapsed working days, not billable hours, which is the number that answers the question people are actually asking.

Waiting on photographs3.5 days
Build and page assembly2 days
Your review and changes1.5 days
Local SEO and schema0.5 day
Live, testing, handover0.5 day

Read the top two bars together and the whole thing makes sense. The part everybody imagines is the website, the actual building of it, is a quarter of the calendar. The part nobody plans for, getting pictures of your own work off your phone and into a folder, is nearly half.

That is why two joiners who order the same site in the same week can go live a month apart. It is not that one build was harder. One of them sent forty photographs on the Monday and the other sent four, then went quiet for a fortnight because he was on a staircase in Guildford.

The clock does not start when you pay, it starts when the photographs land

Seven things start the build, and six of them take a joiner under twenty minutes to gather, which is why an eight day build so often becomes a six week one.

Every hour of a website build after the first depends on content that only you have. Nobody can write the fitted wardrobes page without knowing whether you make them in a workshop or on site, and nobody can build a gallery out of nothing. Send these seven in one go and the eight days hold.

Twenty to forty photographsFinished work, straight off the phone, full size. Not the compressed ones out of WhatsApp.
The two jobs that pay you mostThose get a page each. Everything else shares one. This decides the whole site shape.
Your towns, written outThe actual list, not "the local area". Half of enquiries die on whether you travel that far.
The number that gets answeredThe mobile you carry, not the landline in the workshop you are never in.
Domain login, or who has itIf you do not know, say so on day one. Finding out takes days, and it is the classic last-minute hold-up.
Google Business Profile accessOr confirmation that you have never claimed one, which is its own separate job.
Anything you are certified inTrade memberships, insurance cover, guarantees. These go on the page as proof, not decoration.

Why photographs are the bottleneck and not the copy

Copy can be drafted from a twenty minute phone call and corrected later. Photographs cannot be invented, and stock images of somebody else's kitchen are worse than none. A joinery site sells on the evidence that you make things well: the scribe against a wall that was never straight, the shadow gap that runs true, the end grain on a worktop join. There is no substitute for that in a stock library, which is why the gallery is the one part of the build that genuinely waits on you. I set out exactly what to hand over, and in what format, in what to send your web designer.

Four routes, four very different calendars

The gap between the quickest and slowest route to a live joinery website is not two weeks, it is three months, and the cost ordering does not match the speed ordering.

RouteTypical elapsedYour eveningsYear one cost
Build it yourself
Wix or Squarespace
3 to 8 weeks12 to 20£120 to £250
Local freelancer4 to 12 weeks3 to 5£800 to £2,500
Agency8 to 16 weeks4 to 8£3,000 upwards
Done-for-you plan
What I do
About a week1£650, no build fee

The DIY row is the one worth staring at, because it looks like the cheap option and the evenings column is why it often is not. Twelve to twenty evenings is three to five weeks of your spare time. At a £200 day rate that is real money you have chosen not to see, and it buys a site you then maintain forever. I priced the platforms themselves properly, including what happens when the introductory rate expires, in Wix against Squarespace for a small carpentry business.

The freelancer row is the widest for a reason. Four weeks is a good one with a clear gap in the diary. Twelve weeks is a good one who took your job on while finishing three others, which is the eleven week story at the top of this page and the single most common complaint I hear from UK trades. It is worth reading what should be in a web design contract before you pay anybody a deposit, because a written completion date is the cheapest protection there is.

The three delays that are nobody's fault

Three parts of a UK website build run on somebody else's clock entirely: domain access, Google Business Profile verification, and Google finding the site once it is live.

Domain access

A .co.uk registers in minutes, and it is cheap at wholesale: Nominet, the UK registry, charges its registrars £3.90 a year, and lets domains be registered for anything from one to ten years. The delay is never buying a new one. It is recovering an old one, when the domain was registered years ago by a designer who has since gone quiet, and nobody can remember which registrar holds it. That can take a fortnight of emails on its own, so it is the first thing to check and not the last.

Google Business Profile verification

If you have never claimed your profile, or you are claiming one somebody else set up, you go through Google's verification. Where that is done by video, Google states the review "can take up to five working days". That runs in parallel with the build, which is exactly why it should be started on day one rather than the day before launch.

Google finding the page

Google's own documentation is blunt about this: after you ask for a page to be recrawled, "crawling can take anywhere from a few days to a few weeks". That is before any question of where you rank. Anyone promising a joinery site on page one within a fortnight is describing something Google does not offer.

Live is not the same as found

Going live is day eight, being indexed is usually inside a fortnight, and steady enquiries land somewhere between month two and month six depending on how competitive your towns are.

This is the expectation that most needs setting, because it is where trade websites get written off unfairly. A joiner in a small town in Wales with three competitors may see enquiries inside a month. The same site in a Surrey commuter belt with forty joiners takes longer, and the difference is the competition, not the build.

What shortens it is unglamorous and mostly happens in that half-day marked local SEO on the chart: a page for each thing you actually sell, your towns in writing on the page rather than only in the footer, the Business Profile matching the site exactly, and schema so search engines and AI assistants can read what you do without guessing. Those are the same fundamentals I go through for kitchen fitters, where the money jobs are fewer and the pages have to work harder as a result.

What I would actually plan for. Eight working days to live if you send everything at once. Two to three weeks if you send it in dribs. Then a fortnight before Google has properly found it, and two to six months before it is a reliable source of work. If somebody quotes you faster than that on the last part, they are selling the timeline rather than the result.

What the week actually costs

A done-for-you joinery site is £50 every four weeks with no build fee, which is thirteen payments of £50 across a year, and nothing at all to pay before you have seen it.

The reason the calendar above is eight days rather than eight weeks is that it is the only thing I do. There is no queue of other jobs it sits behind, and there is no version where the deposit is spent and the work is not. You see a free mockup of your own business first, built from your photographs and your towns, before any money changes hands.

After that it is £50 every four weeks and that is the whole cost: the site, hosting, the domain, the certificate, backups and unlimited small text and photo edits, so adding last week's staircase is a text message rather than an evening. Three months minimum, then rolling. After twelve months the website is yours to keep, files and domain transferred, no exit fee. If you want the detail of what actually happens between order and launch, I wrote it up step by step in what happens when you order a trade website, and the full spec for a joinery build sits on the carpentry and joinery page.

Bottom line: eight working days is achievable and three months is common, and the thing that decides which one you get is not the builder's skill or the price you paid. It is whether the photographs are sitting in a folder on day one.

Joinery website build times: FAQ

How long does it take to build a joinery website?

About eight working days from the photographs landing to the site going live, for a seven page joinery site built by somebody who does it full time. Building it yourself on Wix or Squarespace takes three to eight weeks of evenings, because the work happens in the two hours you have left after a day on site rather than in a working day. A UK freelancer typically quotes four to twelve weeks. The build itself is rarely the slow part in any of those routes.

What actually holds up a carpentry website build?

Photographs, in almost every case. On the builds I have done, the single largest block of elapsed time is the gap between agreeing to start and receiving usable pictures of finished work. Everything else is scheduled work that takes as long as it takes. If a joiner sends twenty to forty photographs on day one, an eight day build stays an eight day build. If they arrive in threes over a fortnight, the site takes a fortnight, and no amount of chasing changes that.

How soon will the website appear on Google?

Live and findable are different dates. Google's own documentation states that crawling can take anywhere from a few days to a few weeks after you ask for a page to be recrawled, and that is before any question of where it ranks. Separately, if you are verifying a Google Business Profile by video, Google says that review can take up to five working days. Realistically a new UK joinery site is indexed within a fortnight and starts pulling steady enquiries somewhere between month two and month six.

How much work is it for the joiner?

On a done-for-you build, about one evening in total, spread across sending photographs, confirming the towns you cover, and reading the draft. Building it yourself is the opposite trade: twelve to twenty evenings on Wix or Squarespace for the first version, then an evening every time a job needs adding to the gallery. If your day rate is £200, those evenings are the real price of the DIY route, and they do not appear anywhere on the platform's pricing page.

Can a joinery website be built in a day?

A page can. A site that wins bespoke work cannot, and the reason is not the code. A one day build means stock photography, one generic services page and no page for the two jobs that make you the most money, which is the exact site that gets found by nobody in your part of England or Wales. The eight days are mostly spent on things a rushed build skips: grouping the gallery by job type, writing a page per money job, and putting your towns in writing.

Sources
  1. Google Search Central, Ask Google to recrawl your URLs, for the statement that crawling can take anywhere from a few days to a few weeks. Read 22 August 2026. developers.google.com
  2. Google Business Profile Help, Verify your business with a video recording, for the statement that the verification review can take up to five working days. Read 22 August 2026. support.google.com
  3. Nominet, UK pricing schedule, for the £3.90 per annum registration and renewal fee payable by Nominet registrars. registrars.nominet.uk
  4. Nominet, EPP for multi-year registration and renewal periods, for .uk domains being registrable for one to ten year terms. registrars.nominet.uk
Done-for-you · from £50 every four weeks

Live in about a week, and free to look at first

Send me six photographs and the towns you cover and I will build a free mockup of your actual joinery business. No deposit. If you like it there is no build fee: £50 every four weeks covers the site, the hosting, the domain and unlimited small edits, and after twelve months the website is yours to keep.